Management Statement and Operational Highlights
- Leadership Succession: David Strang steps into Executive Chairman, Makko DeFilippo becomes President and CEO, with Gelson Batista joining to support growth.
- Tucumã: Completed construction and first production in July; executed earning agreement with Vale Base Metals; Phase 1 drill program started with two drill rigs on-site.
- Caraíba: Production increased but development contractor underperformance led to revised guidance; C1 cash costs decreased due to higher grades and favorable exchange rates.
- Xavantina: Strong gold production performance, reaffirmed guidance.
Segment performance
Segment Performance
- Caraíba: Produced 9,920 tonnes of copper in concentrate in Q3, an 11.9% increase. However, underground development underperformance by a third-party contractor led to revising full-year copper concentrate production guidance to 35,000-37,000 tonnes. C1 cash costs decreased 24.5% to $1.63 per pound.
- Tucumã: Completed construction and first production of salable copper concentrate in July. Encountered power issues due to voltage fluctuations and a windstorm, leading to revising full-year copper concentrate production guidance to 8,000-11,000 tonnes.
- Xavantina: Gold production totaled 13,485 ounces in Q3. Reaffirmed full-year gold production guidance of 60,000-65,000 ounces and cost guidance of $450-550 per ounce for C1 cash costs and $900-1,000 per ounce for all-in sustaining costs.
Guidance
Guidance
- Caraíba: Revised full-year copper concentrate production guidance to 35,000-37,000 tonnes.
- Tucumã: Revised full-year copper concentrate production guidance to 8,000-11,000 tonnes.
- Xavantina: Reaffirmed gold production (60,000-65,000 ounces) and cost guidance ($450-550 per ounce C1 cash costs, $900-1,000 per ounce all-in sustaining costs).
- 2025 Outlook: Caraíba expected to underperform initially due to contractor delays, while Tucumã production expected to trend towards higher end of previous guidance.
Risks
Risks
- Operational Challenges: Power issues at Tucumã affecting mill throughput and ramp-up; development contractor underperformance at Caraíba impacting underground development rates.
Q&A highlights
Question and Answer
Q: Ralph Profiti asked about the contractor issues at Caraíba and power issues at Tucama.
A: Makko DeFilippo clarified contractor issues at Caraíba don't affect stope dilution/reconciliation, and at Tucama, the power solution is being addressed with minor capital needed.
Q: Guilherme Rosito inquired about Caraíba guidance and capital allocation.
A: David Strang and Wayne Drier discussed Caraíba guidance being conservative with October showing improvement, and capital allocation priority is repaying revolver then returning cash to shareholders.
Q: Connor Mackay asked about Pilar contractor and Tucama commercial production.
A: Makko DeFilippo said second contractor at Pilar is a risk mitigation measure, and Tucama is expected to reach commercial production within months.
Q: Roald Ross asked about Caraíba cash costs, realized copper price, and Tucama sustaining CapEx.
A: Makko DeFilippo discussed cash cost tailwinds, Wayne Drier explained realized copper price tied to shipment timing, and Makko deferred sustaining CapEx discussion to January guidance.
Q: Dalton Baretto asked about Caraíba contractor root cause and Tucama power solution.
A: Makko DeFilippo cited contractor mobilization delays as the root cause at Caraíba, and David Strang explained the voltage solution at Tucama is managing mill motor sensitivity to voltage fluctuations.
Key numbers
Reported versus consensus
Earnings calendar feed
| Metric | Reported | Consensus | Delta | Prior year |
|---|---|---|---|---|
| EPS | — | — | — | — |
| Revenue | — | — | — | — |
Transcript
November 6, 2024Full transcript unavailable for redistribution
The structured summary above covers the available call sections. Full transcript text is not included on this page.
Continue exploring
Prior quarters
This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.