Summary
Generated 2025-11-04
Management highlights
- Portfolio Management: Thermal generation fleet performance offset lower hydrological conditions, and gas optimization activities supported margin. - Distribution: Implemented winter plan to strengthen grid resilience, including deploying emergency crews, vegetation management, and telecontrol units; supported vulnerable customers. - Regulatory Context: VAD 2024-2028 had key milestones with consultant and preliminary regulatory reports; PAD decree settlement expected in 2026; BESS remuneration resolution in August 2025. - Financial Performance: EBITDA for 9 months remained flat compared to 2024; net income decreased by 21% due to higher depreciation, etc.; FFO improved by $248M compared to 2024; CapEx totaled $245M with allocations to grids, thermal, and renewables/storage.
Segment performance
Generation: In 2025, hydro production was in line with the strategic plan despite a dry year, with thermal production increased using the flexible thermal fleet and strong gas supply, contributing to a $74M margin in the first 9 months. Gas margin in the first 9 months was $27M. Distribution: Successfully implemented a comprehensive winter plan, deploying 376 emergency crews, over 115,000 tree trimming actions, installing new telecontrol units, and supporting over 3,000 vulnerable customers, leading to improved grid performance and service continuity.
Guidance
- Hydrology guidance for 2025 remains unchanged. - Anticipates significant regulatory updates in coming months to clarify tariffs and market mechanisms, which will refine long-term strategy. - Implementing proactive initiatives to address portfolio dynamics and climate challenges, including strengthening generation and distribution, improving risk management, and enhancing response to extreme weather events.
Risks
- Regulatory uncertainties regarding tariffs and market mechanisms that could impact long-term strategy. - Market uncertainties affecting financial results and investment decisions. - Climate challenges posing risks to generation and distribution business operations and service continuity.
Q&A highlights
Q: What is the amount that Enel Chile must return to customers due to the miscalculation of the CNE included in the first half 2026 PNP report?
A: The CNE changed the formula for PNP calculation, and Enel calculated the impact to be between $40 million and $45 million, with customers impacted by a small amount.
Q: What is the amount on to Enel's distribution Chile in connection to the VAD 2000, 2025?
A: The amount is around $50 million to $55 million, with cashback potentially starting mid-2026 but could be faster.
Q: Could you please explain about your strategy regarding LNG and Argentina gas firm or interruptible? For the year 2026, how many ships do you plan to buy?
A: Have a long-term LNG contract with over 32 teraBtu per year; negotiating Argentinian gas contracts, but details not finalized.
Q: Regarding CapEx for generation, could you please give us an update for 2025?
A: Followed CapEx plan with a delay in BESS project due to regulatory changes, total generation CapEx around $150M to $160M, with at least $50M in BESS.
Q: On distribution, could you outline the measures being taken to address the increasing energy losses?
A: Recovering losses more than expected, launching flexible payment plans, localizing loss origins, and working with regulator to contain the phenomenon.
Q: Is the company Enel Chile confirm its latest guidance?
A: Yes, despite tough hydrological year, maintained production using flexibility and gas contracts, confirming results.
Q: Could you explain the dynamics of FFO during the 9 months of this year? And your expectation by the year-end?
A: FFO higher in first 9 months due to PEC receivable recovery, expects improvement in last quarter with efficient net working capital management.
Q: I saw that BESS Las Salinas, 200 megawatts and BESS Acebache, 58 megawatts were declared under construction at the CNE. These projects involve additional solar capacity or just the energy storage?
A: These are hybrid projects with BESS in solar power plants in the North, not increasing solar capacity but equalizing solar projects.
Q: If I'm not mistaken, you had a target of -- for 2025 of $500 million for expansion projects, mainly relating to batteries to storage. How has that changed by now, given that you are expecting a resolution on ancillary services before moving forward? And was the resolution in line with your expectations? Do you think we will be enough to unlock high investment in storage?
A: BESS projects launched during second half, COD in 2026 and 2027; August regulation allowing BESS in service market is good news, helping make BESS profitable and stabilize system.
Q: Do you have any news for unregulated PPA contracts?
A: No news related to unregulated PPA contracts at this moment.
Key numbers
Reported versus consensus
Earnings calendar feed
| Metric | Reported | Consensus | Delta | Prior year |
|---|---|---|---|---|
| EPS | — | — | — | — |
| Revenue | — | — | — | — |
Transcript
November 4, 2025Full transcript unavailable for redistribution
The structured summary above covers the available call sections. Full transcript text is not included on this page.
Continue exploring
Prior quarters
This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.