Cipher Mining Inc. (CIFR) Earnings

Cipher Mining Inc. is expected to report next earnings on August 6, 2026 (in NaN days), with a consensus EPS estimate of $-0.24. CIFR has beaten EPS estimates in 2 of its last 7 reported quarters (average surprise -432.2% over the last four).

Next earnings
Aug 6, 2026in NaN days
EPS est $-0.24 · Revenue est $33M
Track record
Beat EPS in 2 of 7 quarters
Avg surprise -432.2% (last 4 quarters)
Earnings history
Report dateEPS estEPS actualSurpriseRevenueRev. surprise
May 5, 2026$-0.27$-0.28-3.7%$35M-3.5%
Feb 24, 2026$-0.12$-1.92-1500.0%$60M+107.6%
Aug 7, 2025$-0.12$-0.12+0.0%$44M-44.8%
Oct 31, 2024$-0.08$-0.26-225.0%$24M-39.7%
Mar 5, 2024$0.02$0.05+219.9%$43M+3.9%
Mar 14, 2023$-0.07$-0.21-200.0%$3M-34.0%
Nov 14, 2022$-0.07$-0.06+14.3%
Mar 4, 2022$-0.30
Nov 12, 2021$-0.01
Aug 10, 2021$-0.00
May 7, 2021$-0.00
Feb 17, 2021$-0.00

Source: company filings + earnings calendar. For informational purposes only — not investment advice.

Earnings call summary

Q1 FY2026 · May 5, 2026

AI summary of management’s prepared remarks and analyst Q&A. For informational purposes only — not investment advice.

Management highlights

• Corporate milestones: Signed third data center campus lease, completed $2 billion high-yield bond offering for Black Pearl, closed $200 million revolving credit facility. • Physical execution: Barber Lake had over 1,100 daily active workers in April, exceeded 1 million cumulative labor hours with zero lost time incidents; Black Pearl completed demolition of Bitcoin mining infrastructure and phase two broke ground; Stingray site has earthwork and substation work in progress; Odessa's Bitcoin mining performed well in Q1 with healthy cash flow. • Development portfolio: Reveille and Ulysses are advanced pre-contracting opportunities; McLennan, Mekeska, and Colkus are advancing through ERCOT interconnection process.

Guidance

• Contracted cash flow profile: Three executed data center campus leases expected to generate approximately $787 million of average annualized net operating income from October 2026 to September 2036, with $892 million expected in 2035. • Pipeline: Confident in converting pipeline into contracted long-term cash flows, with near-term sites like Reveille and Ulysses targeting energization in 2027 and beyond, and longer-term sites like McLennan, Mekeska, and Colkus expected to energize in 2028.

Segment performance

Not explicitly detailed in terms of absolute financial performance and revenue contribution % for each product segment in a way that can be directly extracted. However, key points include: Odessa is operating 207 megawatts of Bitcoin mining capacity, generating cash flow; Barber Lake construction is well advanced with topping out in April; Black Pearl is progressing with retrofit and construction phases; Stingray site has earthwork and substation work in progress.

Risks & headwinds

• Supply chain disruption risk: While equipment delivery schedules are aligned for Barber Lake, there could be potential risks; also, with ERCOT batch process, uncertainties exist regarding interconnect approvals and site energization timelines. • Operational risk: Uncertainties in the evolution of the Bitcoin mining business and potential challenges in repurposing sites; also, challenges in behind-the-meter on-site generation including engineering, financing, and regulatory hurdles.

Analyst Q&A

  • Q: About pricing and compute thinking,

    A: Pricing trending positively with premium pricing in negotiations, considering potential compute participation at Reveille with credit support developments.

  • Q: Update on Odessa PTA and behind-the-meter strategy,

    A: Odessa PTA has strong economics with potential repurposing, behind-the-meter on-site generation has challenges but is being worked on.

  • Q: Expansion of 100 megawatt contract and exit from Bitcoin mining,

    A: Contract covers 100 megawatts, exit from Bitcoin mining expected by 2027 end with Bitcoin position managed.

  • Q: Equipment outstanding for Black Pearl and lease signing timeline,

    A: Outstanding equipment is commodity-like, lease signing depends on interconnect and construction timelines.

  • Q: Demand for Ulysses site and project-level financing,

    A: Ulysses site has demand with PJM market characteristics, confident in project-level financing with flexible capital structure