DOMINION ENERGY, INC

NYSE · Utilities · Regulated Electric · US

$62.21
−2.12%
Ask drillr
  • Aug 18, 2026, 15:45 UTC

    Dominion Energy split its proposed North Anna to Bristers 500 kV and 230 kV transmission line project into two State Corporation Commission applications, delaying the northern segment that crosses Stafford County to 2027 and the southern segment to fall 2026.

  • Aug 13, 2026, 13:15 UTC

    Dominion Energy filed proposals with the North Carolina Utilities Commission to increase monthly customer costs, potentially raising bills by about $25.73 per month if approved, with an effective date of February 1, 2027.

    Source:
  • Aug 2, 2026, 07:54 UTC

    Virginia rejoined the Regional Greenhouse Gas Initiative (RGGI) carbon market on July 1, 2026, after more than two years away, requiring power plants to buy allowances for carbon emissions.

  • Jul 31, 2026, 19:00 UTC

    Dominion Energy's Coastal Virginia Offshore Wind project reached 81% completion, with 31 turbines installed and a 32nd being installed, and the company increased the project's estimated cost by about 2% to $11.65 billion.

  • Jul 31, 2026, 15:15 UTC

    On July 29, 2026, an electrical fault on a transmission line in Ashburn, Virginia, caused data centers to briefly switch to backup power, removing about 3 gigawatts of demand from the Eastern Interconnection grid.

  • Jul 31, 2026, 00:00 UTC

    Dominion Energy reported Q2 2026 GAAP net income of $340 million ($0.37 diluted EPS) on operating revenue of $4.48 billion, and reaffirmed FY2026 operating EPS guidance of $3.45-$3.69.

  • Jul 28, 2026, 20:20 UTC

    Dominion Energy's board declared a quarterly dividend of 66.75 cents per share, payable on September 20, 2026, to shareholders of record on September 4, 2026.

  • Jul 21, 2026, 22:00 UTC

    Loudoun County School Board is appealing the State Corporation Commission's decision to the Virginia Supreme Court to block Dominion Energy's transmission line over school property.

    Source:
  • Jul 1, 2026, 19:00 UTC

    Dominion Energy is seeking a rate increase due to Virginia rejoining the Regional Greenhouse Gas Initiative, with some lawmakers proposing customer rebates instead of funding energy-efficiency and flood-preparedness programs.

  • Jun 24, 2026, 23:59 UTC

    HanmiGlobal plans to establish a U.S. subsidiary to develop small modular reactor projects.

    Source:
  • Jun 24, 2026, 23:59 UTC

    The Prince William Board of County Supervisors imposed a 90-day deferral on Dominion Energy's Vint Hill substation special use permit.