Management Statement and Operational Highlights
- Montana Project Progress: Completed the first industrial gas well in late October, evaluating results and planning to drill a second well in early 2025. Costs for the initial well were below projections, with expected cost decreases for future drilling.
- Legacy Assets: Sold South Texas properties in July for ~$6.5 million. Net daily production reached 1,149 barrels of oil equivalent per day, with oil accounting for 58% of third quarter production.
- Share Repurchase: Intensified the share repurchase program, with ~886,000 shares repurchased at an average price of $1.17 per share, representing 3% of outstanding shares.
- Balance Sheet: Ended the quarter with zero debt on the credit facility and a cash position of $1.2 million.
- Strategy: Focus on growing the industrial gas platform, strategically monetizing legacy assets, allocating capital to the Montana project, and maintaining balance sheet discipline.
Segment performance
Segment Performance
- Legacy Oil and Gas Assets: Total oil and gas sales for the third quarter were approximately $5 million, a decrease from $8.7 million in the same period last year. Oil contributed 88% of total revenue. Lease operating expense was approximately $3 million, equivalent to $28.95 per BOE. Severance and ad valorem taxes totaled ~$0.3 million. Cash, general and administrative expenses were $1.6 million, a 27% decrease from the prior year. The net loss was $2.2 million, an improvement of $6.6 million from the third quarter of 2023, with adjusted EBITDA at $1.1 million.
- Montana Industrial Gas Project: Completed the first industrial gas well in late October, with evaluation of results ongoing. Plans to drill a second well in early 2025. Initial well came in below projected drilling costs, with expectations of cost reductions in future drilling. This project is positioned as a value driver and foundational step for an industrial gas platform.
Guidance
Guidance
- 2025 is expected to be transformative, with continued work on the Montana project, strategic capital allocation, and potential M&A in the industrial gas space.
- Anticipate full cycle production to sales from the Montana project by early fourth quarter 2025, dependent on plant commissioning.
- Plan to continue the share repurchase activity.
Risks
Risks
- Market fluctuations that could impact revenue and valuations.
- Delays in plant construction or drilling activities affecting the timeline for production and sales.
- Challenges in securing offtake agreements for helium, which could impact revenue projections.
Q&A highlights
Question and Answer
- Q: Remind investors of helium assets online timeline and what's needed.
A: The goal is to get a processing plant in place. Timelines involve drilling 3-5 wells, laying light gathering lines, and commissioning the plant, aiming for full cycle production to sales by early fourth quarter 2025.
- Q: M&A focus, pure-play industrial gas or hold legacy assets.
A: Aim to build an industrial gas platform, divest legacy E&P assets advantageously, and acquire industrial gas-related assets.
- Q: Timeline for helium concentration data and reserve report.
A: Next data points expected in early December/January, with the reserve report from Ryder Scott forthcoming around the same time.
- Q: Helium program revenue/EBITDA outlook.
A: Estimate first plant EBITDA in the $5M-$6M range annually, pending offtake agreement and plant size.
- Q: Helium well costs.
A: First well cost ~$1.8M, expecting costs to decrease by over 30% for subsequent wells.
- Q: Helium pricing outlook.
A: Model ~$400-$450/ton, with potential upside via direct offtake to end users.
- Q: Oil and gas PV10.
A: Around $51 million currently
Key numbers
Reported versus consensus
Earnings calendar feed
| Metric | Reported | Consensus | Delta | Prior year |
|---|---|---|---|---|
| EPS | — | — | — | — |
| Revenue | — | — | — | — |
Transcript
November 12, 2024Full transcript unavailable for redistribution
The structured summary above covers the available call sections. Full transcript text is not included on this page.
Continue exploring
Prior quarters
This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.