Stabilis Solutions, Inc.
Stabilis Solutions, Inc. Q3 FY2025 earnings call
November 7, 2025 · fiscal period ended 2025-09
EPS · actual vs est
Revenue · actual vs est
Summary
Generated 2025-11-07
Management highlights
- Third quarter volume increased by more than 20% YOY driven by strong demand in marine, aerospace, and power generation sectors.
- Secured the largest customer contract in company history, a 10-year marine bunkering contract. Expect to break ground on Galveston facility in Q1 2026 and target it to come online late 2027.
- Plan to construct Jones Act compliant LNG bunkering vessel. Target 75% of Galveston facility capacity sold under long-term contracts by early 2026 FID.
- Worked with engineering partners to secure long lead-time items and finalize equipment contracts. Pursuing joint-venture financing for the project.
Segment performance
Third quarter revenue increased 15% year-over-year. Aerospace revenues increased by more than 88% YOY, power generation by 31%, and marine by 32%. Approximately 73% of total revenue was derived from aerospace, marine, and power generation customers.
Guidance
- Expect to break ground on Galveston facility in Q1 2026 and target it to come online late 2027.
- Aim to have approximately 75% of the total capacity at Galveston facility sold under long-term customer contracts by early 2026 FID.
- Intend to pursue a joint-venture structure for project financing, retaining operational control.
Risks
- Forward-looking statements subject to risks and uncertainties that may cause actual results to differ from projections.
- Uncertainties related to project permitting (e.g., Texas Railroad Commission, Coast Guard) and project financing.
Q&A highlights
Q: Any key permits to watch for the Galveston project?
A: Permits like Texas Railroad Commission for the facility and Coast Guard for the bunkering operation are being tracked, and progress is ongoing.
Q: Details on growth in aerospace and power generation?
A: Aerospace demand up due to increased space activity; power generation demand driven by distributed power needs for data centers. Working on optimizing capacity to meet demand, including plans for additional LNG trains.
Q: Industry of the marine client in late-stage discussions?
A: Could be cruise, container ships, or third-party traders in the bunkering space.
Q: What about the stock block at $5?
A: Stabilis doesn't know who is offering the 100,000 share block at $5.
Q: Is data center demand included in power generation?
A: Yes, distributed power needs for data centers are part of the power generation demand discussed.
Key numbers
Reported versus consensus
Earnings calendar feed
| Metric | Reported | Consensus | Delta | Prior year |
|---|---|---|---|---|
| EPS | — | — | — | — |
| Revenue | — | — | — | — |
Transcript
November 7, 2025Full transcript unavailable for redistribution
The structured summary above covers the available call sections. Full transcript text is not included on this page.
Continue exploring
Prior quarters
This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.