Management highlights

  • WTS Segment Performance: Delivered record financial results driven by a 7% increase in production volume and a 19% increase in selling prices per ton due to favorable product mix changes. The NDA project contributed approximately $31 million in revenue during the quarter. Backlog grew to a record $435 million, indicating strong demand and visibility for future production.
  • Precast Segment Dynamics: Despite a 4% decrease in shipped volume, revenue remained stable due to a 3% price increase. The business successfully pivoted from muted residential construction toward non-residential institutional projects and emerging data center opportunities. Data center bookings exceeded $11 million year-to-date, helping offset softness in other areas.
  • Strategic Acquisitions: Completed the acquisition of Serpentix, a manufacturer of engineered conveyor systems for wastewater treatment. This expands the company’s capabilities in municipal and industrial wastewater solutions, complementing existing dewatering and mixing technologies. Integration is progressing well with current management retained.
  • Operational Efficiency & Safety: Achieved record consolidated net income of $18.2 million ($1.86 per diluted share). Maintained a strong safety culture with a Total Recordable Incident Rate (TRIR) of 0.8. Implemented disciplined cost management and pricing strategies that improved precast margins by 160 basis points despite lower volumes.
View in transcript ↓

Segment performance

Water Transmission Systems (WTS): Revenue reached a record $131.9 million, up 27% year-over-year. This segment contributed approximately 73.6% of total consolidated revenue. Gross profit increased 23.4% to a record $27.3 million, with a gross margin of 20.7%. Precast: Revenue slightly increased 0.6% year-over-year to $47.5 million, contributing approximately 26.5% of total consolidated revenue. Gross profit rose 8.6% to $10.9 million, with an improved gross margin of 22.9%.

View in transcript ↓

Guidance

  • Consolidated Outlook: Management anticipates stronger performance in Q4 2026 compared to both Q4 2025 and Q1 2026, defying typical seasonal headwinds such as holiday shutdowns and weather disruptions.
  • WTS Segment: Expects elevated backlog through year-end supported by continued demand for critical water infrastructure. Full-year base bidding levels (excluding the one-time NDA project) are expected to be stronger than 2025 levels. Additional revenue contribution from the NDA project is expected in Q4 2026 and potentially into 2027.
  • Precast Segment: Expects steady performance in Q4 2026, supported by a solid order book. Anticipates 2026 to be a record year for precast revenue overall, driven by diversity in end markets and growth in data center projects.
  • Financial Metrics Guidance: Full-year 2026 SG&A is expected to range between $55 million and $56 million. Depreciation expense is guided at $22 million to $23 million. Effective tax rate is projected at 23% to 24%. Capital expenditures are expected to be between $21 million and $23 million. Free cash flow guidance for the full year 2026 is set at $62 million to $72 million.
View in transcript ↓

Risks

  • Macroeconomic Uncertainty: Continued uncertainty regarding interest rates and fuel costs is impacting customer decision-making, leading to delayed shipments in the precast segment and muted residential construction activity.
  • Steel Supply Chain: While lead times have begun to moderate, steel lead times remain extended. Fluctuations in steel prices affect revenue recognition and margin dynamics, although current pricing environment supports higher revenues.
  • Project Concentration Risk: A significant portion of recent WTS revenue is derived from the unique NDA project. The absence of follow-on projects of similar scale could create revenue gaps in future periods if not replaced by new bids.
  • Integration Execution: As with any M&A activity, there is inherent risk in successfully integrating Serpentix and capturing anticipated strategic benefits and synergies within the wastewater platform.
View in transcript ↓

Q&A highlights

Q: Analyst asked for details on the data center pipeline, including shipped vs. booked volumes, margin profiles compared to traditional work, and outlook for 2027. / A: Management confirmed data center margins are generally higher than standard precast orders. The pipeline is growing, with quoting levels rising and shipping following bookings. These orders are filling gaps left by slow residential and commercial markets, allowing facilities like Geneva to pivot from ~85% residential to ~40% residential, balancing with non-residential and data center work. Project sizes are expanding significantly, with recent bids reaching $3-5 million, up from historical $300k-$400k averages, driven by substantial construction activity in Texas alone.

Q: Analyst inquired about the NDA project's remaining value, potential bleed into 2027, and whether WTS can maintain flat revenue in 2027 without this 'pig in the python' one-time boost. / A: The total NDA project value was approximately $56 million, with ~$40 million recognized so far. Management expects ~$16 million in Q4 2026, with some potential bleed into early 2027 depending on contractor pace. Regarding 2027, while replacing the NDA gap entirely is challenging, underlying momentum is tremendous. Even excluding NDA, WTS was up 10-12% year-to-date. Bidding remains very strong, and most 2027 production needs are already secured in backlog, suggesting another strong year despite the loss of the one-time project.

Q: Analyst asked about the sustainability of the improved contract liability days (pre-billing) in WTS and how it impacts forward free cash flow trends. / A: CFO noted that pre-billing days dropped to 99 from 150 last year, which may not be fully sustainable long-term but reflects a fundamental shift in cash flow prioritization. This metric is tied to compensation incentives, ensuring commercial teams drive collections aggressively. While it may moderate back toward the 150-day range, the sentiment and focus on improving cash conversion remain ingrained in the business strategy.

Q: Analyst sought clarification on the composition of the WTS backlog growth, specifically the split between volume-based increases and price-based increases (steel costs), and how steel price locks impact future margins. / A: Management clarified that backlog growth is driven by both volume and price. Revenue per ton is up 19%, while steel prices are up 12%, indicating volume and favorable mix play larger roles than just steel inflation. Because contracts often lock in steel prices earlier, the backlog includes older, lower-cost steel commitments alongside newer ones. This provides visibility and protects margins, as the revenue side benefits from higher volumes and pricing power beyond just raw material pass-throughs.

View in transcript ↓

Key numbers

Reported versus consensus

Earnings calendar feed

MetricReportedConsensusDeltaPrior year
EPS$1.86$1.66+12.2%—
Revenue$179.4M$168.0M+6.7%—

Transcript

October 29, 2026

Full transcript unavailable for redistribution

The structured summary above covers the available call sections. Full transcript text is not included on this page.

Continue exploring

Prior quarters

This page presents the stored structured earnings-call summary and deterministic earnings calendar values. How this is generated. For informational purposes only; not investment advice.