Largo Inc. Q3 FY2024 earnings call

November 14, 2024 · fiscal period ended 2024-09

EPS · actual vs est

/

Revenue · actual vs est

/
Ask about this call

Summary

Generated 2024-11-14

Management highlights

Production - Delivered highest quarterly vanadium production in seven quarters (3,072 tonnes), up 42% y-o-y. - Ilmenite production ramped up, with 16,383 tonnes produced in Q3, a 90% increase from the previous quarter. ### Cost Management - Reduced operating costs by 31%, maintaining a competitive position in the vanadium sector. - Cash operating costs excluding royalties decreased by 43% y-o-y. ### Commercial Strategy - Francesco D'Alessio promoted to Chief Commercial Officer, implementing a refreshed sales strategy to optimize inventory and build customer relationships. ### Technical Report - Recently announced technical report highlights update showed a 67% increase in mineral reserves and 64% increase in mineral resources, expanding mine life to 2054. ### Largo Clean Energy - Advancing discussions with Stryten Energy for a potential joint venture in vanadium flow battery technology, leveraging Largo's vanadium flow battery tech and Stryten's manufacturing/market reach.

View in transcript ↓

Segment performance

In Q3 2024, Largo's vanadium production was 3,072 tonnes, up 42% from Q3 last year. Revenue was $29.9 million, with $27.2 million from vanadium sales (91% of total revenue) and $2.7 million from ilmenite sales (9% of total revenue). Operating costs were reduced by 31%, and cash operating costs excluding royalties were $3.12 per pound sold, a 43% reduction from the previous year.

View in transcript ↓

Guidance

Production - Confident in meeting full-year 2024 production, cost, and sales guidance. ### Vanadium Supply Agreement - Vanadium supply agreement unlocks ~$23.5 million of additional liquidity from vanadium inventories upon delivery between Q4 2024 and Q1 2025. ### 2025 Outlook - Expect cost improvements to continue, with prices in the US market potentially recovering faster than in Europe. - Ilmenite production to ramp up with lower costs when production and recoveries are optimized, aiming for $0.30 to $0.50 per pound vanadium production costs when fully optimized.

View in transcript ↓

Risks

  • Market Volatility: Soft demand in Europe and oversupply in the Chinese market impacting vanadium prices. - Geopolitical Factors: Impact on vanadium supply from certain regions affecting US market access. - Ilmenite Ramp-up: Still in ramp-up phase, need to optimize recoveries and production for cost reduction.
View in transcript ↓

Q&A highlights

Q: Where is the demand for vanadium coming from and when will it impact results?

A: Demand is mainly from the aerospace sector in the US, with impacts expected in 2025 contracts.

Q: Outlook on vanadium prices in 2025?

A: Expect a 2-tiered market with higher prices in the US due to limited supply from other regions.

Q: Cost outlook for ilmenite production per pound?

A: When ilmenite production is ramped up and optimized, expect costs in the $0.30 to $0.50 per pound range for vanadium production.

Q: Debt and status of Majorca storage facility?

A: No debt attributable to Majorca storage facility; final commissioning of the battery system is in the final stages.

View in transcript ↓

Key numbers

Reported versus consensus

Earnings calendar feed

MetricReportedConsensusDeltaPrior year
EPS
Revenue

Transcript

November 14, 2024

Full transcript unavailable for redistribution

The structured summary above covers the available call sections. Full transcript text is not included on this page.