Golar LNG Ltd.
Golar LNG Ltd. Q3 FY2026 earnings call
November 18, 2026 · fiscal period ended 2026-09
EPS · actual vs est
Revenue · actual vs est
Summary
Generated 2026-11-18
Management highlights
Fleet operations and projects
- Gimi maintained strong performance despite warm summer conditions and scheduled maintenance; 50 cargoes have been completed. Management expects long-term overproduction of roughly 10%-15%, with further no-investment optimization potential of 1%-3%.
- Hilli left Cameroon for Singapore dry dock. Conversion work for its Argentina contract is on time and on budget, with arrival expected in mid-2027 and startup under a 20-year contract.
- Esperanza’s midsection has been joined to the front and aft sections. Construction remains on time and on budget for year-end 2027 delivery; the project has logged more than 20 million work hours without a lost-time incident.
- Argentina’s supporting infrastructure and regulatory milestones are progressing on time and on budget. CESA has sold its first 2 million tons to Securing Energy for Europe and is in advanced discussions for the next 3 million tons.
Growth and commercial strategy
- FLNG 4 is targeted for delivery by year-end 2029, which management describes as the earliest available global liquefaction capacity and two to three years ahead of alternatives. Charter discussions are advanced, targeting a roughly 20-year contract.
- Golar reserved long-lead items for a potential FLNG 5 and secured shipyard capacity, but intends to have only one FLNG under construction at a time.
- Management sees FLNG as a flexible, capital-efficient alternative to onshore LNG for many projects and cites growing demand for diversified LNG supply. The company controls 12.1 million tons per year of liquefaction capacity and has options and arrangements for additional construction capacity.
Financial position and shareholder returns
- Golar added approximately $1.6 billion of liquidity through a $600 million revolving credit facility, a $500 million senior unsecured bond, and an expanded Hilli sale-leaseback facility. Available liquidity is approximately $2.3 billion.
- Golar is pursuing approximately $1.8 billion of long-term financing for Esperanza, which could release about $1.2 billion of additional liquidity.
- The company declared a $0.25-per-share quarterly dividend, has a share buyback program, and reiterated its disciplined capital allocation approach.
Segment performance
Golar reported Q3 operating revenue of $84 million, down from $130 million in Q2, mainly because Hilli completed its Cameroon contract and operated for only one month in the quarter. EBITDA was $56 million versus $127 million in Q2, while net income was $42 million; year-to-date net income reached $200 million, more than double the comparable prior-year period. The transcript does not provide revenue contribution percentages by product segment.
- Gimi: The sole operational FLNG during the quarter. It produced 3% above contractual levels in Q3 and had invoiced 12% above its contractual base year-to-date. Its base annual EBITDA contribution is approximately $150 million, before commodity-linked upside.
- Hilli: Completed its eight-year Cameroon contract in late July, delivering 156 cargoes and 100% economic uptime over the contract. It generated $8 million of commodity-linked earnings in Q3 and $55 million year-to-date. Its anticipated annual EBITDA in Argentina is $285 million before commodity upside and inflation adjustments.
- Esperanza: Under construction, with no current operating revenue. Its projected annual EBITDA contribution is approximately $400 million once operational.
- FLNG 4: FID was taken during the quarter; the unit is not yet operational and contributes no current revenue. Estimated capex is $2.45 billion. If contracted on terms similar to Esperanza, it could contribute to annual EBITDA above $1.2 billion for the fleet overall.
Guidance
- Hilli’s Argentina conversion remains on schedule and on budget; arrival is expected in mid-2027, followed by a 20-year contract. Its annual EBITDA is expected to be approximately $285 million before commodity upside and inflation adjustments.
- Esperanza remains on schedule and on budget for year-end 2027 completion and a mid-2028 contract startup. Its projected annual EBITDA contribution is approximately $400 million.
- FLNG 4 is expected to deliver by year-end 2029. Management is targeting a long-term charter similar to the other units; on comparable terms to Esperanza, fleet annual EBITDA could rise by about 50% to above $1.2 billion by 2030.
- With Gimi, Hilli, and Esperanza operating, management expects approximately $800 million of annual run-rate EBITDA by 2028, before commodity upside and inflation adjustments. At $10/MMBtu, illustrative annual EBITDA could be about $1.4 billion; at current gas prices, about $2.6 billion. Pricing levels seen in 2022 could imply nearly $4 billion in a particular year; these are scenarios, not forecasts.
- Gimi’s expected sustained overproduction is approximately 10%-15% over time. Management expects higher Q4 overproduction due to colder ambient temperatures and less scheduled maintenance.
- Management expects to conclude sales discussions for the next 3 million tons of Argentina production within Q1 next year.
- The Hilli financing amendment is expected to close in December, with approximately half a billion dollars of net proceeds; additional drawdowns toward a facility size of up to $1.2 billion are expected in 2027 and early 2028.
- FLNG 5 will not reach FID until Golar has clear visibility on a contract for FLNG 4. Management expects potential further FLNG FIDs in the broader market and has secured long-lead items and yard options to protect its own delivery schedule.
Risks
- Golar’s current operating cash generation depends heavily on Gimi: it is the only operational FLNG until Hilli returns to service in Argentina. Hilli’s Cameroon contract ended in July, reducing operating days and Q3 revenue and EBITDA.
- Gimi’s production is affected by seasonal ambient temperatures and scheduled maintenance across the wider GTA infrastructure. Management expects summer production to remain relatively lower, even with sustainable annual overproduction.
- FLNG growth requires substantial capital and timely access to shipyards and scarce long-lead equipment, particularly compressors and dual-fuel engines, which also face demand from AI data-center construction. Delays or cost pressure could affect delivery plans.
- FLNG 4’s projected economics and growth contribution depend on securing a long-term charter; commercial discussions are advanced but no contract was announced. FLNG 5’s FID is explicitly contingent on visibility for FLNG 4.
- Project execution remains exposed to construction, financing, and infrastructure delivery. Management reported no current schedule or budget slippage at Hilli or Esperanza, and no lost-time incidents on Esperanza to date.
- The company’s illustrative EBITDA scenarios are sensitive to commodity prices; commodity-linked earnings can vary materially with LNG prices. Argentina’s contracted economics also include inflation adjustments and depend on associated infrastructure and offtake arrangements.
Q&A highlights
Q: What is the timing and commercial trigger for FLNG 5, and how is FLNG 4 being contracted? / A: Golar will not FID FLNG 5 until it has clear visibility on a contract for FLNG 4, maintaining its policy of only one open FLNG project at a time. It reserved scarce long-lead equipment to protect delivery timing; FLNG 4 discussions target a roughly 20-year, US-dollar contract with client-covered or reimbursed operating and maintenance costs.
Q: Is Q3 a representative baseline for Gimi’s summer output, and what optimization remains? / A: Management expects sustainable average overproduction of 10%-15%, but summer output will continue to be affected by heat and planned maintenance. No-investment improvements may add 1%-3%; larger debottlenecking gains would require investment and agreement on cost sharing with upstream partners.
Q: What donor-vessel characteristics will Golar seek for future conversions? / A: It favors Moss-design LNG carriers for their ability to operate in a wider range of sea conditions and their attractiveness as conversion candidates. For future units, management is weighing vessel cost against storage capacity and expects to consider vessels at least as large as Esperanza, approximately 145,000 cubic meters or more.
Q: Where does FLNG remain competitive against land-based LNG? / A: Management sees FLNG as competitive on capital cost up to roughly 6-10 MTPA and favorable on operating cost for projects below roughly 10-15 MTPA. Very large developments of 30-40 MTPA may favor onshore facilities, while management views projects such as Argentina’s proposed 12 MTPA FLNG build-out as evidence of the floating model’s competitiveness.
Q: How does management view share repurchases at current prices? / A: The existing buyback program remains available, and Golar has historically been more active when its shares weaken, subject to trading restrictions when it holds material non-public information. Management said the share price was about 25% below its peak for the year and described the current valuation as attractive.
Key numbers
Reported versus consensus
Earnings calendar feed
| Metric | Reported | Consensus | Delta | Prior year |
|---|---|---|---|---|
| EPS | $0.22 | $0.04 | +469.4% | $0.43 |
| Revenue | $83.7M | $79.4M | +5.4% | $122.5M |
Transcript
November 18, 2026Full transcript unavailable for redistribution
The structured summary above covers the available call sections. Full transcript text is not included on this page.