Globalstar, Inc. (GSAT) Earnings

Globalstar, Inc. is expected to report next earnings on August 6, 2026 (in NaN days), with a consensus EPS estimate of $-0.03. GSAT has beaten EPS estimates in 4 of its last 12 reported quarters (average surprise -124.6% over the last four).

Next earnings
Aug 6, 2026in NaN days
EPS est $-0.03 · Revenue est $72M
Track record
Beat EPS in 4 of 12 quarters
Avg surprise -124.6% (last 4 quarters)
Earnings history
Report dateEPS estEPS actualSurpriseRevenueRev. surprise
May 7, 2026$-0.02$-0.16-700.0%$70M-1.2%
Nov 6, 2025$-0.01$-0.01+0.0%$74M+4.7%
Aug 7, 2025$-0.09$0.13+244.4%$67M-2.7%
May 8, 2025$-0.07$-0.10-42.9%$60M-7.0%
Feb 27, 2025$-0.05$-0.14-180.0%$61M+1.6%
Nov 7, 2024$-0.00$0.04+3092.9%$72M+20.0%
Aug 8, 2024$-0.15$-0.15+0.0%$60M+5.6%
Feb 28, 2024$-0.00$-0.15-6566.7%$52M-0.9%
Nov 2, 2023$-0.01$-0.03-200.0%$58M+9.1%
Aug 3, 2023$-0.15$0.00+100.0%$224M+335.3%
May 5, 2023$-0.15$0.15+200.0%$59M+18.6%
Mar 1, 2023$-0.01$-0.03-99.9%$41M+6.6%

Source: company filings + earnings calendar. For informational purposes only — not investment advice.

Earnings call summary

Q4 FY2025 · February 27, 2026

AI summary of management’s prepared remarks and analyst Q&A. For informational purposes only — not investment advice.

Management highlights

• 2025 was transformational with record full-year revenue and 50% adjusted EBITDA margin. • Focused on scaling core business and laying foundation for growth. • Launched two-way satellite IoT capabilities and completed commercial rollout of RM-200MS module. • Secured early government and defense wins, expanded in multiple verticals. • Achieved proof of concept with Parsons, advanced XCOM RAN-based 5G research. • Fireworks awarded Phase II SBIR contract leveraging Globalstar's XMRI5 platform. • Expanded global ground station network, advanced ITU financial commitments, and XCOM RAN ecosystem. • Average commercial IoT subscribers up 6%, IoT hardware sales revenue up 50%.

Guidance

• Expect total revenue between $280,000,000 and $305,000,000 in 2026 with an adjusted EBITDA margin of approximately 50%. • Confident in continued growth trajectory as scaling next-generation infrastructure and expanding commercial opportunities. • C3 constellation critical design review completed, work ongoing on ground network buildout and regulatory side. • Two-way IoT capabilities in process of being adopted by customers, module in mass production. • Pipeline for XCOM RAN includes warehouse automation, CBRS, military use cases, stadiums, convention centers, military bases.

Segment performance

Full Year 2025: Total revenue reached a record $273,000,000, up 9% from 2024. Service revenue was $257,300,000, up 8%, driven by increased wholesale services. Subscriber equipment revenue was $15,700,000, up 24% due to higher commercial IoT device sales. Income from operations was $7,400,000 vs. a loss of $900,000 in 2024. Net loss improved to $7,600,000 from $63,200,000 in 2024. Adjusted EBITDA was $136,100,000, a 50% margin. Q4 2025: Total revenue $72,000,000, service revenue $67,400,000 (up 17%), equipment revenue $4,600,000 (up 31%). Loss from operations $400,000 vs. $4,200,000 in Q4 2024. Net loss $10,600,000 vs. $50,200,000 in prior year. Adjusted EBITDA $32,400,000, up 7% from prior year's quarter. Balance sheet: Cash and cash equivalents $447,500,000, operating cash flows $621,700,000, capital expenditures $550,400,000, adjusted free cash flow $171,500,000. Principal debt balance $410,000,000 at year-end.

Analyst Q&A

  • Q: Thoughts on data centers in space?

    A: Not focused on that, but understand industry excitement, but technical challenges exist.

  • Q: Next milestones for C3 constellation?

    A: Critical design review done, work on ground network buildout and regulatory side.

  • Q: XCOM RAN customer KPIs with Boingo?

    A: Throughput in dense environment, running over DAS, warehouse automation ease of deployment and capacity sharing.

  • Q: MSS and terrestrial 5G flexibility with S-band spectrum?

    A: Synergy due to global harmonized spectrum, working on multimode capability for satellite modems.

  • Q: Targeted launch windows for replenishment satellites?

    A: First launch in second quarter, second launch in second half.

  • Q: When two-way communications services went live?

    A: Customers building out solutions, module commercial but waiting on customers to finish applications.

  • Q: Government pipeline and longer-term guidance?

    A: Pipeline has near-term and newer opportunities, near-term revenue from network buildout for other regions.

  • Q: Ground infrastructure upgrade for longer-term MSS network?

    A: Committed to ITU to spend $2,000,000,000, halfway through, buildouts going well.