US Hyperscaler Datacenter Equipment Suppliers

Who supplies the power and cooling equipment behind new US hyperscaler datacenter campuses?

· The user wants to know which companies supply power and cooling equipment for US hyperscaler datacenter campuses. Let me search for this using company_search_tool and also list_tables for data center related tables.

The supply chain behind new US hyperscaler campuses (Microsoft Fairwater, Meta Prometheus, OpenAI Stargate, Amazon Ridgeland, etc.) splits cleanly into four layers:

Power Management & Distribution
Power Management & DistributionETNEaton Corp$172.8B
Switchgear, PDUs, UPS, busway, critical power infrastructure
Broad hyperscaler supply — Microsoft, Amazon, Google, Meta
Power Management & DistributionVRTVertiv Holdings$104.0B
Power distribution units, UPS, DC power systems, busway
Named supplier to major US hyperscalers; AI datacenter ramp key growth driver
Power Management & DistributionVICRVicor Corp$9.6B
High-density power modules, 48V bus converters for AI racks
GPU rack power delivery — Nvidia-driven demand
Power Management & DistributionENSEnerSys$6.8B
UPS batteries, VRLA / lithium backup power
Supplies backup power to top US hyperscalers
Thermal / Cooling Equipment
Thermal / Cooling EquipmentVRTVertiv Holdings$104.0B
Precision air cooling (CRAC/CRAH), liquid cooling, CDUs
Air-cooled chiller leader by product count in AI DC specs
Thermal / Cooling EquipmentMODModine Manufacturing$10.1B
Precision air conditioning, liquid-cooled heat exchangers
Hyperscale and AI datacenter cooling systems
Thermal / Cooling EquipmentAAONAAON Inc.$7.3B
Rooftop and precision cooling units for datacenters
DC-specific HVAC product line; growing hyperscaler wins
Thermal / Cooling EquipmentSPXCSPX Technologies$10.6B
SPX Cooling Technologies — wet cooling towers (largest modeled footprint)
Dominant cooling tower supplier in AI DC equipment specs
Alternative / On-site Power Generation
Alternative / On-site Power GenerationBEBloom Energy$62.0B
Solid-oxide fuel cells for baseload on-site power
OpenAI Stargate New Mexico (Oracle campus); Microsoft partnership
Alternative / On-site Power GenerationSEISolaris Energy Infrastructure$3.9B
Mobile gas turbines leased to hyperscale campuses
Bridging grid capacity gaps at new campuses
Electrical Contracting / Integration
Electrical Contracting / IntegrationEMEEMCOR Group$35.7B
Electrical & mechanical construction, datacenter buildout
Largest US electrical contractor; major DC campus backlog

Key dynamics by layer:

Power Management — Eaton (ETN) and Vertiv (VRT) dominate. Eaton covers the full switchgear-to-PDU stack; Vertiv is the dominant precision power + cooling vendor appearing in the most AI datacenter equipment specs. Vicor (VICR) is the niche play: its 48V bus converters are embedded inside AI racks at the GPU level, a position that scales with Nvidia GPU density.

Cooling — The shift to liquid cooling is the structural story. Vertiv and Modine (MOD) both supply coolant distribution units (CDUs) for direct-to-chip liquid cooling — the required architecture for GPU clusters drawing 100kW+ per rack. AAON supplies the rooftop air-side economization layer. SPX Cooling Technologies (SPXC subsidiary) is the single largest supplier of cooling towers by product model count in actual AI campus specs, handling the wet-side heat rejection for chillers and CDUs.

On-site Generation — Bloom Energy (BE) is the most interesting: fuel cells are already contracted for the OpenAI Stargate New Mexico campus (Oracle-owned) and a Microsoft partnership. Grid interconnect queues now run 5-7 years; on-site fuel cells let campuses reach 400-600MW without waiting. Solaris Energy (SEI) fills a shorter-term gap by leasing mobile gas turbines to cover construction-phase power needs.

Construction Integration — EMCOR (EME) is the single largest electrical and mechanical contractor for US datacenter buildouts. It converts all the above equipment into operational campuses.

Real-world project energy exposure from facility data: Georgia Power (Microsoft Atlanta, 636 MW), American Electric Power (Meta Prometheus + OpenAI Stargate Abilene, 1,052 MW combined), Memphis Light/Gas/Water (xAI Colossus, 340 MW), Dominion Energy (QTS Richmond campus, 562 MW combined). These are utilities, not investable pure-plays, but they confirm where the load growth is concentrating.


Sources: AI datacenter facility and equipment specifications database; chiller and cooling tower manufacturer specifications database; analyst consensus and market data.

Figures as of the run date (Aug 11, 2026) · sources cited inline · information, not investment advice